Package XL02 of the Ho Chi Minh City - Long Thanh expressway expansion project, spanning nearly 12km through Dong Nai province, has been largely completed - Photo: A Loc
On November 16th, Mr. Pham Thanh Hai, Director of the Southern Expressway Project Management Unit (SEPMU), announced that Package 2 of the Ho Chi Minh City - Long Thanh Expressway expansion project , the section passing through Dong Nai province, has been basically completed.
According to Mr. Hai, most of the sections under package number 2 have been paved with three layers of asphalt, and the remaining sections are expected to be completed by November 16th. The contractor is currently constructing expansion joints at bridge locations, painting road markings, installing signs, guardrails, and lighting systems.